P200 Primary Mirror Backsupport Status Update 27 Feb We are happy to report that we were back on the sky for testing with P200 this week. As the weather would allow, the telescope delivered excellent image quality (e.g. ~ 1" early Tuesday and Thursday nights), and no signs of the mechanical hysteresis that the refurbishment aimed to correct. The team took a large amount of image and extra-focal data (so as to assess the primary mirror figure), and will be working through that data in the coming days. At this point we will go forward with the announced schedule of contingency observers, and are optimistic that the mirror will continue to perform well. Congratulations and thanks to Jeff Zolkower, Hal Petrie, Keith Matthews, Dan McKenna, and the entire observatory staff for their outstanding planning and execution of the P200 Mirror Backsupport refurbishment. Update 21 Feb: As of Friday 19 February all 36 mirror supports have been removed, refurbished, and re-installed into the telescope. On Friday morning we started the process of mechanical adjustment of the supports for axial, azimuthal, and lateral position. We should be finished with these adjustments on Monday morning. Over the weekend we are bringing the mirror back down to the nighttime ambient temperature in preparation for on-sky testing. Depending of the weather forecast for Monday night, we will prepare the telescope for observing and optical testing, or if on-sky tests are unlikely, keep it in a mechanical testing mode with the Cass cage removed. A series of mechanical tests have been planned in case the weather does not cooperate. Our first contingency observers are scheduled for Sunday 28 February; pending the outcome of image quality tests this week we believe it is highly likely that the telescope will be ready for a return to science operations to support contingency observations. Update 13 Feb: As of Friday afternoon (12 Feb), 31 of the 36 mirror backsupport assemblies have been removed, refurbished, and re-installed in the telescope, with an additional two refurbished assemblies waiting for re-installation. Only one unrefurbished unit needs to be removed from the telescope. We estimate that the refurbishment work will be finished by Wednesday afternoon (in the holiday-shortened week). After the last unit is installed, we will begin the process of support system adjustment, involving axial, azimuthal, and lateral tuning of each support relative to the mirror and each other. We estimate this process will take two days. During this adjustment period, we will turn off the heaters, and begin to cool the dome, telescope structure and mirror. Our present schedule is to begin on-sky testing, tuning, & verification on 22 Feb. Update 5 Feb: At present (5 Feb) 17 (of 36) mirror supports have been removed, refurbished, and replaced (two more are presently out of the telescope and being refurbished). To date the refurb crew has averaged processing roughly 2 supports/day. This (17/36, 2/day) is actually slightly ahead of our projected status +and+ rate for this point on the refurb activity, and all signs indicate that we will complete the refurb on or slightly ahead of schedule. The crew is performing extremely well, and is taking a well-deserved weekend off to watch the SuperBowl! --- Last Updated: 27 February 2010 AFB