Timeline for Milestones |
|
June 2005 |
| 13 - Project Start |
|
July |
| TBD - All-Hands Project Meeting |
|
August |
| 1-6 - Jarle and Bob
visit to Caltech |
|
September |
| 13 - Draft Initial
OCDD Due to TMT Project Office |
|
October |
| 13 - Draft Initial
FPRD Due to TMT Project Office |
|
19 - IRMOS Mtg at UCSC |
|
November |
| 13 - IOCDD Due to TMT |
|
December |
| 13 - IFPRD Due to TMT |
|
January 2006 |
| 13 - Feasibility Study
Report (FSR) Outline Due |
| TBD - TiPi All Hands
Project Meeting |
|
February |
| 15 - FSR Due to TMT
(change to original SOW) |
|
March |
| 16 - IRMOS-TiPi
Feasibility Study Review by TMT Project |
|
April |
| 14 - Revised Final FSR Due to TMT
(see 2/15/06) |
|
September |
| 25-29 - TMT Project
Cost Review |
| September 2007 |
| 24-28 - TMT Project
Preliminary Design Review (PDR) |