Assumptions
The following steps should have been completed during the instrument setup and
are described in more detail in Setup Procedures.
- The dewar and electronics rack are mounted on the telescope and are
correctly cabled.
- The SC-10 pick-off mirror and chopping secondary have been correctly
wired.
- The SC-10 beam has been accurately aimed at the secondary.
- Cryogens are sufficient for the night.
- Detector electronics have been checked for proper DC and clock voltages.
- GSM electronics have been approximately calibrated.
- The Sun workstation (GRB) has been booted and the ethernet cable
to the PC and the serial port connections to the telescope computer and printer
are in place.